Latest on Barrier highway closure
Submitted: Monday, Mar 05, 2012 at 11:14
ThreadID:
92310
Views:
2222
Replies:
4
FollowUps:
3
This Thread has been Archived
Dave B ( BHQ NSW)
Just came over the radio that the Barrier Highway
bridge at
Cockburn is expected to be open in about 2 weeks.
The road between
Broken Hill and Olary is closed until then.
The only option from
Broken Hill to
Adelaide or Pt
Augusta is via
Wentworth -
Renmark.
cheers
Dave
Reply By: Member - Andrew L1 (SA) - Monday, Mar 05, 2012 at 17:59
Monday, Mar 05, 2012 at 17:59
We walked over the
bridge on the Barrier Hwy yesterday. You can see a dip in the guard rail on the left side where the road way has sunk.
AnswerID:
479555
Follow Up By: Member - Andrew L1 (SA) - Monday, Mar 05, 2012 at 18:01
Monday, Mar 05, 2012 at 18:01
Image Could Not Be FoundSorry forgot the photo
FollowupID:
755017
Follow Up By: Holden4th - Monday, Mar 05, 2012 at 20:05
Monday, Mar 05, 2012 at 20:05
Thank you Andrew for the photo. As I've said in another thread, I'm due in
Cockburn on the night of April 2 to cross the
bridge on April 3. I hope they haven't run out of beer.
FollowupID:
755027
Reply By: Great Divide Tours - Tuesday, Mar 06, 2012 at 13:13
Tuesday, Mar 06, 2012 at 13:13
Bugger, I was due to cross it next Sunday on my way to the
Simpson Desert, looks like a long detour via
Wentworth, unless the road via
Loch Lilly on the border to Oakvale in SA is open, anyone know?
Vic
AnswerID:
479613
Reply By: Dave B ( BHQ NSW) - Tuesday, Mar 06, 2012 at 20:09
Tuesday, Mar 06, 2012 at 20:09
Today we were told that the Barrier Highway will be open again on March 16th.
There will be a temporary structure over the top of the damaged
Pine Creek bridge at
Cockburn.
cheers
Dave
AnswerID:
479663
Reply By: neil777 - Tuesday, Mar 13, 2012 at 10:56
Tuesday, Mar 13, 2012 at 10:56
according to an ABC report on 9 March the road should be open now
http://www.abc.net.au/local/stories/2012/03/09/3449609.htm
can anyone confirm that
we are leaving from
Sydney on 19 March to head to
Perth and would prefer to go through
Broken Hill than through all the water down the Riverina way
AnswerID:
480252
Follow Up By: Dave B ( BHQ NSW) - Wednesday, Mar 14, 2012 at 10:05
Wednesday, Mar 14, 2012 at 10:05
As reported on the ABC and another post in the
forum on this subject, the Barrier Highway was opened at 5PM.
cheers
Dave
FollowupID: